[Gnso-epdp-team] EPDP Project Package - 31 Mar. 2020
policy at bacinblack.com
policy at bacinblack.com
Thu Apr 2 12:40:01 UTC 2020
Dear All,
Please find attached the EPDP-Phase 2 Project package that closes out March
of 2020.
The project health remains on a "Revised Schedule" and "On-Target". The
percent complete reports at 92% with an 81% elapsed time from when the
project started. This is up 11% from last period due to the close of the
public comment period, close out of tasks related to Priority 2 items and
completion of staff related tasks. Do not let the 8% remaining fool you. We
have a fair amount of comments to review, review comments from the Addendum
report, form final agreements on proposed recommendations, perform a
consensus call, and review the text of the Final Report.
You can find separated work products on the wiki:
https://community.icann.org/x/6BdIBg
Thank you.
Berry Cobb
@berrycobb
GNSO Policy Consultant
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mm.icann.org/pipermail/gnso-epdp-team/attachments/20200402/db395046/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: EPDP-P2_Project_Package_20200331.pdf
Type: application/pdf
Size: 473036 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/gnso-epdp-team/attachments/20200402/db395046/EPDP-P2_Project_Package_20200331-0001.pdf>
More information about the Gnso-epdp-team
mailing list