Dear all, 

We made some progress yesterday. Unfortunately, that progress was about getting back to where we were after Brussels, rather than making real progress. 

I created a new table during our work session yesterday. 

The table (https://docs.google.com/spreadsheets/d/1pfLFG9nixw_JEZBBdErw9McLpXHfigVjPR4u3O4OxZ4/edit#gid=0) describes the recommendation status in the v3 recommendation document (https://docs.google.com/document/d/10KOW2F6oqR3OdV7hfuWmnYo6gtE0d0wOZHOQzXmijx4/edit#). 

As you can see, most recommendations have been ported (status PORT) but may need discussions or other team action (see “Action” column). Actions required per our discussion in Marrakech are entered, feel free to add.

Some are missing from the new document (status MIS). If you are the penholder, please edit, review, and port to the new document BUT ONLY THE NEW, EDITED, READY FOR PLENARY REVIEW, text. 
Make sure if a MIS recommendation needs to be merged with other recommendation in the old document (https://docs.google.com/document/d/1CsuEYzQHve6a5rKQNeMQbjoyujdUQa9g__9_ojoqDBM/edit#)

Some recommendations have status DROP, meaning that we dropped them, or usually that they are (to be) merged into other recommendations. 

ACTION ITEM: 
1. Please review the table. If you are the penholder for a recommendation with status MIS, merge, edit, and port as required. 
2. Check the table and new text; add comments to table and document (comment mode) 
3. Complete actions if possible. 
4. Update table accordingly

Many thanks
Laurin 