[CWG-Stewardship] Reminder: Comments on WorkPlan due Friday 5 December at 23:59 UTC

Grace Abuhamad grace.abuhamad at icann.org
Fri Dec 5 04:24:23 UTC 2014


All, 

Just a reminder that the Chairs have asked for any comments/suggestions to
the work plan to be submitted by Friday 5 December at 23:59 UTC. I've
reattached their note and copied it here below for your convenience.

Best, 
Grace

IANA Stewardship Transition Cross Community Working Group (CWG) on Naming

Related Functions 

Work plan update from the CWG co-chairs for members and participants Lise
Fuhr & Jonathan Robinson

The Chairs recognize the great amount of work that has been done drafting
the proposal sent out for consultation and we thank the group for the
effort. However, given the demanding schedule we still need to work with, we
cannot rest on our laurels if we are to meet our next major objective of
having a submission ready for the chartering organizations by 19 January
2015. 

As per our plan we are presenting 3 webinars on the public consultation
document this week. Given 2 of these webinars are on Thursday 4 December
2014 and would be book-ends to our working group meeting and that your
co-chairs will be presenting the webinars, we felt this was too much. As
such we are cancelling the Thursday 4 December meeting of the CWG and hope
that those that have questions on the proposal will attend the webinar.

Although the 4 December meeting is cancelled, we are posting this new
schedule of meetings to allow us to reach our objective, which will include
continuing our CWG meetings during the holiday period:
* 
*   Thursday 10 December 2014 – 11:00UTC
* 
*   Thursday 18 December 2014 – 11:00UTC (Time change from 14:00 to 11:00)
* 
*   Tuesday 23 December 2014 – 14:00UTC - hour to be confirmed
* 
*   Tuesday 30 December 2014 – 14:00UTC - hour to be confirmed.
* 
*   Thursday 8 January 2015 – 11:00 - UTC - hour to be confirmed
* 
*   Saturday 10 January – Time TBC (New additional meeting inserted)
* 
*   Thursday 15 January 2015 – 14:00UTC - hour to be confirmed.
* 
* In addition to the above, we now need to focus our efforts on the tasks
that still need to be completed in order to meet our next objective. To this
end we would propose the following schedule:

 Public consultation

o Prepare weekly reports on the public consultation for the CWG – Support
staff.
o Prepare a final report and analysis of the results of the public
consultation for the CWG for the

30 December meeting – Support staff.
o Review by the CWG of the results of the public consultation and identify
action items resulting

from – 30 December meeting.
o Draft and post the results of the public consultation per the results of
the CWG review – 5 

January – Staff support.

 RFP3 – Contract Co.

o Obtain formal legal advice regarding viability of concept and initial
requirements – GS and volunteers.

o Contract details 

 Review key terms and make decisions regarding these after details of the
MRT are settled. 

 RFP3 – MRT 

 RFP3 – CSC 

 RFP4 

o Complete functional analysis and derived requirements – GS and Staff will
prepare a report for CWG consideration at its 10 December meeting.

o Composition requirements - GS and Staff will prepare a report for CWG
consideration at its 10 December meeting.

o Structural (internal functional) requirements - TBD o Support requirements
(secretariat etc.) - TBD
o Bootstrap requirements – TBD

o Complete functional analysis and derived requirements – GS and Staff will
prepare a report for CWG consideration at its 10 December meeting.

o Composition requirements – CWG (10 December 10).
o Structural (internal functional) requirements – CWG (10 December). o
Support requirements (secretariat etc.) – CWG (10 December).
o Bootstrap requirements – CWG (10 December).

 RFP3 – Independent Appeals Panel

o Wait for results of public consultation.

 RFP5 

 RFP6 

o Complete a list of proposed changes from RFP3 (confirmed and optional)
that are to be considered in this section –Staff (5 December)

o For each proposed change in the previous list identify which of the
elements of RFP4 apply and have to be developed to meet the requirements.
Present report to CWG – RG, SM (10 December).

o Prepare a complete evaluation for one of the simple proposed changes for
presentation to the CWG on 10 December – RG, SM.

o Present additional elements at each of the following meetings of the CWG
on December 18, 23, 30 - RG, SM.

o Present a final draft at the 8 January meeting of the CWG.

o This work will be completed by the drafting team when the other elements
are being 

assembled. 

o Is being developed by staff with the help of the various communities. A
draft of this is Section C of the public consultation document. This should
be completed in the final drafting sessions in the week of 12 January.

Furthermore the Principles need to be finalized and this is to be done by 10
December. They will be sent out for comments as soon as possible.

We realize that this is a demanding schedule and acknowledge the commitment
required of members, participants and staff in working within this schedule,
especially as it impacts on the calendar year end holiday season for many.

Comments, suggestions and improvements to the proposed schedule are welcome
but please provide these as soon as possible and in any event by 23:59 UTC
on Friday 5 December 2014.


From:  Jonathan Robinson <jrobinson at afilias.info>
Organization:  Afilias
Reply-To:  Jonathan Robinson <jrobinson at afilias.info>
Date:  Wednesday, December 3, 2014 9:11 AM
To:  "cwg-stewardship at icann.org" <cwg-stewardship at icann.org>
Subject:  [CWG-Stewardship] Workplan update from the CWG co-chairs for
members and participants

All,
 
Please see attached for a work plan update from the CWG co-chairs for
members and participants and including detail on proposed meetings and times
(some of which have changed).

 

Note: Tomorrow’s meeting of the CWG (4 December 2014, 14:00 UTC) will no
longer go ahead as planned. Please check the attachment for full details.

 

Thank-you,

 

 

Lise Fuhr & Jonathan Robinson

 


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20141205/92fe0805/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 725BBD97-65CF-4510-A946-A769CF544948.png
Type: image/png
Size: 2737 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20141205/92fe0805/725BBD97-65CF-4510-A946-A769CF544948-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: A23A2CB3-5BDD-4DE4-8990-56CFC77D940E.png
Type: image/png
Size: 2737 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20141205/92fe0805/A23A2CB3-5BDD-4DE4-8990-56CFC77D940E-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: CWG Workplan 03 December 2014.pdf
Type: application/pdf
Size: 186715 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20141205/92fe0805/CWGWorkplan03December2014-0001.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: smime.p7s
Type: application/pkcs7-signature
Size: 5097 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20141205/92fe0805/smime-0001.p7s>


More information about the CWG-Stewardship mailing list