Dear Yuko

Tks

Pls kindly advise the timing of the CWG Calls and possibly include them in
the Mater plan CCWG CALLS

I am lost in the middle of multiple schedules plans

It Is urgent

Regards

Kavouss

2016-08-11 2:28 GMT+02:00 Yuko Green <yuko.green at icann.org>:

> Dear CWG-Stewardship,
>
>
>
> The Naming Function Agreement is now posted for 30-day comment period at:
>
>
>
> https://www.icann.org/public-comments/iana-naming-function-
> agreement-2016-08-10-en
>
>
>
> Regards,
>
> Yuko Green
>
>
>
> *From:* cwg-stewardship-bounces at icann.org [mailto:cwg-stewardship-
> bounces at icann.org] *On Behalf Of *Trang Nguyen
> *Sent:* Wednesday, August 10, 2016 2:35 PM
> *To:* cwg-stewardship at icann.org
> *Cc:* Samantha Eisner <Samantha.Eisner at icann.org>
> *Subject:* [CWG-Stewardship] Version 2 of Naming Function Agreement
>
>
>
> Dear CWG-Stewardship,
>
>
>
> Attached is a revised Naming Function Agreement that incorporated feedback
> from Sidley. We will start a 30-day public comment process on this draft
> today. During the public comment period, we will continue to engage with
> the CWG and Sidley to resolve any remaining issues or concerns with this
> document as we have been for this and other documents. We are also
> preparing documents that will explain how we have taken on Sidley’s
> feedback and how we have incorporated the principles of Annex C. These
> documents will be provided to the CWG over the next few days.
>
>
>
> Here is a schedule of the public comment period to give you visibility of
> the timeline:
>
>
>
> 10 August: Public comment period begins
>
> 11 August: CWG meeting
>
> 18 August: CWG meeting
>
> 25 August: CWG meeting
>
> 1 September: CWG meeting
>
> 9 September: Public comment period ends
>
> 16 September: Staff analysis report and final Agreement posted
>
> 16 September: ICANN Board meeting
>
> TBD: PTI Board meeting
>
>
>
> ICANN Board approval of the Agreement is expected to take place on 16
> September. The PTI Board will also be asked to approve the Agreement.
>
>
>
> Best,
>
>
>
> Trang
>
> _______________________________________________
> CWG-Stewardship mailing list
> CWG-Stewardship at icann.org
> https://mm.icann.org/mailman/listinfo/cwg-stewardship
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mm.icann.org/pipermail/cwg-stewardship/attachments/20160811/a93986f6/attachment.html>


More information about the CWG-Stewardship mailing list