[Gnso-epdp-team] EPDP Project Package - 31 May 2020

policy at bacinblack.com policy at bacinblack.com
Thu Jun 4 14:58:09 UTC 2020


Dear All,

 

Please find attached the EPDP-Phase 2 Project package that closes out May of
2020. 

 

The percent complete reports at 96% with an 94% elapsed time (to 30 June
2020) from when the project started. Percent complete is up 2% from last
period mostly attributed to the completed review of the public comments to
the Initial Report.

 

As of the 31st of May, the project health remains on a "Revised Schedule"
and "On-Target". As you will see on the summary timeline, the project SitRep
(page 3), and as noted in the workplan sent around the last few weeks, the
EPDP will miss its 11 June target for delivery of the Final Report. The EPDP
Leadership team is preparing a Project Change Request (PCR) to notify the
GNSO Council, which is now a requirement from the implementation PDP3.0. As
a part of the PCR and based on results of "can't live with items," the
leadership team will also confirm/modify a new planned delivery date.

 

You can find separated work products on the wiki:
https://community.icann.org/x/6BdIBg 

 

Thank you.

 

 

 

Berry Cobb

@berrycobb 

GNSO Policy Consultant

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mm.icann.org/pipermail/gnso-epdp-team/attachments/20200604/defacb73/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: EPDP-P2_Project_Package_20200531.pdf
Type: application/pdf
Size: 512074 bytes
Desc: not available
URL: <http://mm.icann.org/pipermail/gnso-epdp-team/attachments/20200604/defacb73/EPDP-P2_Project_Package_20200531-0001.pdf>


More information about the Gnso-epdp-team mailing list